Silt management on construction sites with constrained linear footprints

We make use of interceptor ditches to design passive, low carbon, rain-ready silt management systems for linear construction sites to prevent pollution. 
Categories:
Gel Flocculant Guidance Note Pollution Avoidance & Mitigation Silt Control

Bringing innovation to ditches on construction sites to trap and manage silt 

By their nature linear construction sites involving railway lines, roads and pipe lines often have a constrained or restricted footprint. The topography tends to be challenging with narrow boundaries stretching vast distances.

On these types of sites there is usually little room for attenuation ponds or settlement features to help manage silty water during construction work.

Silt site visit

Zero energy systems that respond to rain

Our innovative approach prevents erosion by controlling the water flow on site, focussing it into managed ditches containing Silt MatTMFloc MatsTM Rock Checks and Silt Wattles that help slow the flow of the water and remove sediment from the water.

These systems are passive and require no energy to run. They can be put in place ahead of rain to protect sites from silt pollution at any time of year.

We use other gravity-fed rain-ready products to enhance sediment separation from water such as Gel Flocculant placed in pipes located in ditches. This technique binds solids together which drop out of suspension.

Rain activates these systems and the products require minimal maintenance, however monitoring is recommended as part of your water management plan.

IMG_0642 (Large)
IMG_9306 (Large)

Retain soils on site, release clear water from site

As dirty water moves along a ditch, we want to be able to transfer those solids into a state where they can settle, allowing us to trap them or separate them out. This then leaves us with clear water that is safe to emit into rivers, streams or other watercourses.

When working in these environments we need to think about where we are using water, and how we stop it from running off-site, where it could cause harm to the environment or flood neighbouring land.

We aim to move clear water off site and retain the silt and sediment onsite.

Innovative approaches to treating water on sites constrained by size

We are leading the way in capturing and treating site water by using interceptor ditches when there is limited capacity to store water within the site boundary. We are further developing these processes for non-linear situations, saving space on other constrained sites and enhancing the performance on attenuation ponds or lagoons.

We are creating new, innovative techniques such as using smaller interceptor features, called catch pits, which we use at frequent intervals along a ditch.

Frog Environmental has developed novel techniques to slow the water down, treating it with Gel Flocculant, which causes the sediment to accrete, and then dropping it out into the ditch or onto a Silt Mat or Floc Mat.

We also help you understand your soil structure and make up. Understanding the particle size of your silts is very important when writing your Surface Water Management Plans.

Lagoon polishing with floc and silt mats (Large)

Reusing Floc Mats and Silt Mats as erosion control on site

The biodegradable silt mats will silt up over time, at which point they can be replaced, and the silt-laden ones can be used to protect exposed soils elsewhere on-site by pinning or laying them out.

They can be seeded, or if left they will vegetate naturally, whilst protecting the soil from erosion. They can also be used around hedgerow or tree planting as biodegradable, moisture-retaining and weed suppression.

Incorporating this as part of a materials management plan that considers waste regulations will meet compliance and provide an excellent way to retain the nutrient-rich soil on site.

Rain Ready® site solutions

Site assessment and ground investigation can be complex, but for the purposes of understanding whether a flocculant is likely to be needed during temporary works, we can ask the following two questions:

Will site drainage during construction be connected to ditches, streams, brooks or rivers?
Will any top soil be removed, exposing a clayey sub-soil during works?

If the answer to both these questions is ‘yes’, it is advisable to engage with environmental support, as your site is likely to be at a higher risk of causing a silt pollution event.

Attenuation ponds versus linear ditch systems?

We would always prefer to design in attenuation ponds because they create capacity in the system to cope with the spikes in water flow. But there are times when we do not have the ideal situation and are working within physical constraints, this is where we become more creative.

We recommend early consideration in the project to understand each dynamic phase, for example, exploring how the site topography will change so that we can create a plan to allow for this.

Low carbon, passive solution

These low-carbon systems evolve with the changes in the site. This helps us resolve many issues which could be costly if not anticipated and dealt with at each stage. It also avoids the use of pumps, meaning that the energy use in the project is zero, and the system is always ready to go whether you are on-site or not.

Leela O’Dea, director at Frog Environmental, spoke at the IECA conference, in Spokane, Washington in February 2024.

“Thanks to Frog’s technical expertise and insight, we have found new ways to tackle these common issues and improve our site water management practices – from company-wide awareness and training to monitoring and prevention. As a consequence, we have made significant cost savings and lowered our carbon emissions.” 

Paul Thomas, Head of Environment
Winvic Construction

logo-winvic

“The results (of the bubble curtain) were quite dramatic – in fact, startling… we have a workable solution that we’ve proved has a dramatic impact on noise propagation.” 

David McLaren, Site Manager – Marine & Civils
John F Hunt Regeneration

testimonial

It’s good to see Frog getting involved with GT at the earliest stages of the project to help with planning out water management in advance of needing it.

Galliford Try

GT

I really enjoyed learning how to identify which measures are best suited to the site conditions.

TACP (UK) Ltd

Tac

“Frog Environmental were knowledgeable, helping to establish a workable, cost-effective and low maintenance solution for site approved by the regulator. They really understood the water management issues we had on site and worked with us to develop a solution which works, as well as engaging with our operatives to ensure that they could effectively manage the system.

We are delighted to have found a solution that prevents pollution and protects the environment, and ultimately allows us to continue with construction.”

Glenn Entwistle, Senior Environmental Advisor
Advance JV

1630479036967

The surface water system drainage feature utilised innovative solutions from Frog Environmental.

A rain-ready strategy was implemented, which enabled the development of a robust management system capable of effectively managing fluctuations in weather conditions year-round.

This provided a timely, sustainable and cost saving solution for our client.

Anthony Jordan
RSK Geosciences

RSK_Geosciences_logo_CMYK

“The positive impact of your business on the wider industry is incredible. You have upskilled so many of us and definitely improved water quality across UK construction sites!”

Bernadette Anderson, Environmental Manager
VolkerLaser

VL

Frog’s commitment to develop innovative, market-leading strategies to help their construction clients take responsibility for their sites has and is inspiring an industry-wide change in management culture to improve environmental practices. Of note is their “Rain Ready” water treatment system which is setting new benchmarks in environmental excellence.

Brad Griko, VP Operations
Clearflow Group

CF Inc Back Blue.

“The systems were very effective, and we can see how they could be used on other projects. Being able to talk through the scenario with Frog Environmental was really helpful… We were so pleased to be able to proceed with this essential works with no disruption to either wildlife or our workplan, it saved us time, money, and provided peace of mind that we had taken effective steps to protect the environment.”

Huw Williams, Site Agent
Morgan Sindall Infrastructure – Water & Highways

MS

They (Frog Environmental) were efficient in providing advice and the most appropriate product for our project. The team responded promptly to ensure the Bubble Curtain was delivered to the site on schedule.

It has worked well and has been great on site. We are demobilising this week, and the bubble curtain is already in store at our next site for reuse!

Hayley Jackson, Site Agent
Coffey Group

Coffey

The Kex Gill road realignment scheme is a challenging project with multiple environmental risks including management of silt and water quality of the surrounding environment given the locality of designated sites.

Frog Environmental are providing us with extensive technical support, including the design, supply and install of their silt control products on site to ensure the project minimises risks to the watercourses in the project vicinity and prevents impact on highly sensitive aquatic species.

It’s great to be working with them and we’re delighted with the success of the whole project.

Georgina King, Associate Director
RSK Environment

RSK

Working with you

To support our clients most effectively it is helpful for us to be involved as early in the project as possible.

The sooner we are involved the earlier we can put in silt interventions that will save significant amounts of money, whilst working out whether the project is a low-risk water management project or an elevated risk one; either way, forward planning reduces costs in the short and long term.

At the start of the project, we work on:

  • Understanding the topography of the site
  • Understanding how that topography will change over the course of the project
  • Understanding the soils
  • Getting involved at the archeology stage, if possible, to prevent unnecessary exposure of soils and to immediately prevent early pollution and erosion risks
  • Understanding the catchment of the area to create the water exit plan
  • Putting in place a water management plan that adapts to the lifetime of your project
  • Planning how we will turn dirty water clear and take it off site
  • Whether Silt MatsTM or Floc MatsTM can be used on site as further long-term erosion control and reducing off site waste as a part of the Materials Management Plan

We offer free training on the risks of silt on a construction site and you can download our Silt Control Toolbox Talk to communicate key points to your team. We can also help you understand why your soil structure and particle size is important and offer support around mitigations when looking at SWMPs.

Bringing our water quality and silt control specialist team of consultants on board early allows you to prevent issues arising; through training up your staff, offering technical design and site preparation support, as well as products that are engineered to meet needs across a wide range of industries.

We offer a non-obligatory call or Teams meeting with our Technical Team to talk through your needs at any stage of your project to see where we or our environmentally-friendly product solutions may help.

For products, services, training and technical sales support contact us or call 0345 057 4040.

Contact Us

Disclaimer: This article is correct at the time of writing and while we endeavour to update annually, legislation may change over time. We pride ourselves on providing site-specific advice. Please contact us about your situation; we’d be delighted to help.

Constructionline
Acclaim logo
Achilles Network Stamp Gold
company-badge
IECA_MemberlogTagline_Global (2)
SafeContractor- RGB- navy
SafeContractor-Certification Seal